What is Vk and Imag i.e Knee point voltage & Magnetising
Current?
How to calculate above values?
How to define accuracy class 5P10?
Answer Posted / zahid ali
Vk is knee point of CT it mean when 10% increase in voltage
varies the current 50% at that point we determine the knee
point voltage. In othe words excitation test of CTs,
connect a single phase variable power supply leads to the
CT seccondary leads k & l or s1, s2 along with ampere meter
& voltage meter & than apply voltage start from zero &
raise incremental simultaneously draw a graph on each
increments by plotting current on X-axis & voltage on Y-
axis.
Magnetizing current is those which is used in core & tank
of transformer due to leakage flux, which is furthur
devided into hysteris losses & eddy current losses.
We can find magnetizing current by open circuit test.
5P10 means: 5 for composite errors in percentage, P for
protection & 10 mean overlaod factor by multiply 10 times
in others words CT will not saturate by passing 10 times
higher current.
| Is This Answer Correct ? | 84 Yes | 9 No |
Post New Answer View All Answers
what is the differebt between ac and dc fuse?
Can I use distributon class/transmission class Lightning arresots for protecting the building? If not why please explain?
When the relative speed between the magnetic fields of stator and rotor does is zero under steady state operation?
can mini-curcuit supply MIL-tested transformer !
Give accurate definitions for these electric terms: Inductor Inductance Inductive Induction Reactance Reactive Esam Baraka ٢١ ساعة
at work we have a 3 phase motor but on testing one phase isnt getting a reading. it runs 24 hours a day all week. stops and starts well no noise or heating. the phase isnt down to earth.is it just a bad meter reading or not? phases one and three came up with a resistance reading of 0.4 but phase 2 couldnt get anything shows up as open circuit.
percetans
Difference between low impedance and high impedance Restricted Earth Fault
What are the relays in ACB and VCB
What is Electrical Grade Aluminum for Tubular BusBars. i am confused between 6063 and T6 or T5 and what is BS 2898 and BS 159?
what exactly commisioning work does in electrical site work... LT side?..
when will be the iocl interview results i faced interview on 8th september 2008 iam from electrical branch i faced interview for the post of electrical engineer??????????????????????//
what are the installation procedure of high voltage power transformer,CT,CB&PT?
What are the main parts of central chiller plant? Explain the function of each stage.
What are marginally stable systems?