Questions Answers Category Views Company eMail




Answers / { shankar }

Question { IBM, 2495 }

a guy hired 5 men to work on a project and they completed
the job in 13 days. IF, on the 4th day, 2 men resigned,
then how long would they complete the job?


Answer

30 days

Is This Answer Correct ?    0 Yes 0 No