Question { IBM, 34550 }

how cubic feet cement,sand,aggregate required for 1 cubic feet
ratio=1,1.5,3


Answer

cement=403.5kg
fa=.42cum
ca=.84 cum

Is This Answer Correct ?    2 Yes 2 No

Question { 6401 }

What is the difference in Cement content for M-20 Concrete
if y ou use OPC & PPC?
What is the difference in the Curing Period?


Answer

for opc =10 days
for ppc=14 days

Is This Answer Correct ?    0 Yes 1 No


Question { 6801 }

What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).


Answer

2*1.54/7=0.44 m3

Is This Answer Correct ?    1 Yes 0 No

Question { L&T, 10620 }

how many rods to be require in kg 10sq.m slab?


Answer

800 kgs