During which of the following phases in systems development
would user acceptance test plans normally be prepared?

A. Feasibility study

B. Requirements definition

C. Implementation planning

D. Post-implementation review

Answer Posted / guest

Answer: B

During requirements definition, the project team will be
working with the users to define their precise objectives
and functional needs. At this time, the users should be
working with the team to consider and document how the
system functionality can be tested to ensure it meets their
stated needs. The feasibility study is too early for such
detailed user involvement and the implementation planning
and post-implementation review phases are too late. The IS
auditor should know at what point user testing should be
planned in order to ensure it is most effective and efficient.

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHICH OF THE FOLLOWING IS OFTEN AN ADVANTAGE OF USING PROTOTYPING GOR DYDTEM DVELOPMENT

2836


purchase orders issued to vendors have been authorized as per the authorization matrix

1086