what are the basic parameters considered in designing a
pavement?
Answer Posted / amit
The CBR has to be between 12 and 30 . Additionally ,
compaction prior to laying a new pavement is of great
importance . In case soil is Clayey , the whole area will
need to be excavated ,removed and replaced with sandy soil.
Traffic will undoubtedly play an important role and based on
CBR and Traffic Intensity , the apprpriate curve will have
to be selected. traffic intensity will be calculated for a
period of 20 years.
| Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
what is stressing
what will be density of a cement bag if its weight and volume are 50kg and 1.25 cft respectively???????
Is there any course for billing available in Mumbai? If yes then please mail me the details..
pls give me ans to ACT formula cube testing porpuse
Discuss some applications of modular elasticity?
What are the ingredients of pre-stressed concrete?
How cracks in concrete can be avoided?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
What is the tensile strength of marble?
How can i do RCC rate analysis?
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
If specific gravity of cement is less than 3.15 what is the cause?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above