WHAT HAPPEN WHEN CT SECONDARY OPEN DURING LOAD
Answer Posted / ashish s. hans
If the CT secondary open during load than the voltage across
the secondary reaches to a high value i.e some kilowatts and
the secondary current becomes zero hence reduced back emf.
The working flux increases and core gets saturated. The
secondary e.m.f increases due to increased flux
Due to the above reason the primary gets overheated and core
also gets heated and its dangerous for person working on
secondary
| Is This Answer Correct ? | 52 Yes | 11 No |
Post New Answer View All Answers
What is miller crystal oscillator? Explain its operation?
how freewheeling diode improves the powerfactor
What is steady state response?
Why PT voltages are measured with respect to ground? What do u mean by voltage or current polarized.
IF TVM OF TRANSFORMER SHOWS POWER FACTOR ON 33 KV SIDE AS 0.97 LAGGING AND ON 132 KV SIDE IS 0.75 LEADING.IS THIS CORRECT.WHERE IS PROBLEM.
What are the main advantages of generalized error co-efficients?
how open delta PT works & what is its construction?
I have made a 3 phase thyristor full bridge rectifier. But at the moment it is working only for the half bridge operation. Both the half bridges are on operation separately but when i put it into full bridge operation the oscilloscope output is zero. I rechecked that the pulses are correct for each thyristor. what could be the possible reason for this?
sir, i am 3 years diploma course pass out candidate.what type of certificate can i got in marine service.
how to deside the capacity of chock for drive?
What are the necessary solutions needed to be carried out on a malfunctioned earthing mechanism of a VACUUM CIRCUIT BREAKER.(TAMCO)
What is line resistance of cable & how it can be measured ?
What is the exact minimum vale of voltage between an earth and netural which can damage or can do malfunction of the electronic equipments ? If this is mentioned in any book, pl.give reference.
Can anyone tell me some hints about what type of questions are asked by the interviewer by an Electronics engineer when company is installing an IPP and wants a team of engineers?
How to do cable earhing? whether by grounding Armour to ground or by running extra G.I wire along with cable? which one is preferred mostly amoung them? If the second one is more preferable how many GI wires to be run along with cable (1 or 2)?