how bridge design is to be start?
what is the preliminary step for design?
which code of practice is to be used for design?
what r the methods used for design?
what r the ivestigation r carried out?
what r the design criteria for design and loading conditions?
Answer Posted / rajkumar
Hi friend,
Designing of bridges goes in following steps:
1) selecting suitable location after sufficient geographic
survey, hydrological survey, geological survey,etc.
2) after selecting the location you have to decide what
type of bride will be suited for ex. steel or arch or RCC
or prestressed, etc. depending upon length of bridge,
geological conditions, purpose etc.
3) once the type is decided then comes the part of load
considerations as under:
* DL, LL, Wind induced Loads, Earthquake induced loads,
hydraulic forces, centrifugal forces if any, upthrust,
stresses due to thermal changes etc etc...
* for this some IRC Specifications are to be followed.
4) after load calculations and various load combinations
the individual members are to be designed.
I hope this answers your question....
for more information look out in text "Bridge Engineering
by S.P.Bindra"....
Is This Answer Correct ? | 14 Yes | 1 No |
Post New Answer View All Answers
How much is the cover for slab?
what else we can add rather than admixture in concrete to reduce the cement quantity?
what is tension footing?
What is the average density of soil?
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
what is work of planning deptt. in any construction compny (in road project)
Why concrete barriers have curved surface profiles?
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
How to calculate cement and river sand material Qty for waterproofing base coat and finish coat
why we are useing plastic under the lean concrete?and whts the advantage?
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
all technical question
how much cement and sand consuptin in 4 inch siporex walls 100 sq ft