Hi
Once the tester finds the issues the tester give the
status of the issues is NEW
Then the tester assigned to developers then status of
issues is Assigned
Then the developers open issues then the status of issues
is OPEN
After the issues is fixed and gives the modify build
Then tester testing the issues is fixed are not? If fixed
the status of issues is FIXED
If you not fixed the status of issues is REOPEN
Some times based on priority and severity the developers
give and (tester ) status will be changes like deferred
| Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
What are different types of verifications?
Can you do system testing at any stage of sdlc?
I want to know about satyam manual testing questions
What about manual testing opening in bangalore in September. Not getting a single interview call from last one month.
What is Test Design?
What are the benefits of requirement traceability?
Write positive and negative test cases for forgot password?
1.What is bidirectional traceability ??? and how it is implemented? 2.What is Automation Test frame work ? 3. Define the components present in test strategy? 4. Define the components present in test plan? 5. Have u written Test plan ?…. thank u!plz reply........
What is user acceptance testing (uat)?
Who are all involved in an inspection meeting?
Can you explain a pair-wise defect?
In interview How do explain in Testcase of Calcuator,Cellphones, Email testing?
1)can u tell me, what is the roles and responsibles for database tester in DB testing from requirement stage to UAT stage....2) what are the i/p documents he wants and who wil give the i/p docs. to DB tester.and tell me what exactly db test case means what?
how to connect oracle with test director? in testdirector we will be getting only reports? pls answer Thanks in Advance
what is the relation between all tabs in quality center & explain the testing process in quality center with tabs?