In case you receive a story on the last day of the sprint to test and you find there are defects, what will you do? Will you mark the story to ‘done’?
Answer Posted / Ishwar Singh Gwal
If a story is discovered with defects on the last day of the sprint, it should be addressed as soon as possible. The Scrum Team should not mark the story as 'Done' because doing so would violate one of the core principles of Scrum - delivering potentially shippable increments every Sprint. Instead, prioritize fixing the defect over accepting new work and make adjustments to the next sprint as needed.