how to Concrete cubes testing curing time 7 days
casting date 24.05.17
testing date ?

Answer Posted / Ranjan Kumar Singh

To find the testing date for concrete cubes, you add 7 days to the casting date (24.05.17). The calculated testing date would be 31.05.17.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

2428


HOw much % of premium on DSR-2013 currently

2051


can i get civil engineering test papers.......?????

2550


kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com

1923


400 ku d/c clearess ketan hota hai?

2124


I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.

2510


material used for mendrel use to bend epoxy coated rebar

2246


minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?

5529


how can we calculate steel value, depending on load

2444


can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now

2240


Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?

2087


water leak detection system question & answer

2526


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

2425


Why do you want to work here

2451


can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???

2063