What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
Answer Posted / Vishal Kumar Pandey
If the HDPE duct and cone size in a prestressed girder are provided more than the required dimensions, it may lead to several issues:n
1. Increased cost: Larger ducts and cones require more material, leading to increased costs.
2. Reduced efficiency: Excessive duct and cone sizes may not allow for proper stress distribution, reducing the overall efficiency of the girder.
3. Reduced capacity: A larger cross-sectional area due to oversized ducts and cones can lead to a reduced load-bearing capacity of the girder.
4. Potential safety concerns: If the excess material protrudes beyond the intended area, it may pose a risk during construction or in service.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
what is the 0 value in quantity surveying
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
VAT and CST ? Which benefits for buyer ? Why benefits?
hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
what is the difference between replacement of cement by groundnut shell ash
Technical Question of Civil Engineering
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
I need to constructive work in amaraj batteries