Suppose you planning to paint newly fabricated workshop
building made of structural steel of 10 tons total mass.
How many litters paint primer for 1 coat and 2 coat of top
coat?
Answer Posted / Gaurav Wadhawan
To determine the amount of paint required for a workshop building, we need to know the surface area of the structure. However, since the question mentions a steel structure without providing details about its size or specific shapes, it's impossible to provide an accurate calculation.
Typically, for industrial painting projects like workshops, you would use a combination of primer and topcoat paint. The coverage rates for each coat can vary depending on the brand and quality of the paint. For example:
- Primer: 10-20 square meters per liter
- Topcoat: 5-15 square meters per liter
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Which is the latest version of solidsworks?
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com
pls mail some more tecnical qustions at msaranya2610@gmail.com
What is Density of cement, sand & aggregate ?
water leak detection system question & answer
please send me bhel questions on rupesh.017@rediffmail.com
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
VAT and CST ? Which benefits for buyer ? Why benefits?
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
What is the per cu. mt. price of ready mix in Gujarat region.?
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
material used for mendrel use to bend epoxy coated rebar