how to calclate the SHUTTERING TAKEN CONCRETE LOAD?
WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE?
WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE.
PLATE SIZE IS 120CM* 90CM
CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M
PLS TO SENT THE CALCULATION.

Answer Posted / Shailendra Chandra

To calculate the concrete load in a steel shuttering plate, we first need to determine the volume of concrete and then convert it into mass. Here's the step-by-step process:

1. Calculate the volume of the concrete slab:

Volume = Length * Width * Height = 10m * 60cm * 1.2m = 720 cubic decimeters (or liters)

2. Convert the volume to mass using the density of concrete, which is approximately 2400 kg/m³:

Mass = Volume * Density = 720 m³ * 2400 kg/m³ = 1,728,000 kg (approximately)

3. The load-bearing capacity of the steel shuttering plate depends on its material, dimensions, and manufacturing process. To find out the exact load-bearing capacity, you should refer to the manufacturer's specifications or perform a structural analysis.

4. The concrete load in the shuttering plate can be calculated by distributing the total mass of the concrete slab evenly over the surface area of the steel shuttering plate:

Load per square meter = Total Mass / Surface Area

In this case, the surface area is: 120cm * 90cm = 10,800 cm² (or m²)

Load per square meter = 1,728,000 kg / 10,800 m² = 161.4 kg/m² (approximately)

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.

2493


material used for mendrel use to bend epoxy coated rebar

2246


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

2211


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 100 microns?

1618


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

2400


hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having

2601


Draw a neat sketch showing the 'throat' of a welding in a plate girder ?

2546


Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in

2107


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

2241


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2237


Which is the latest version of solidsworks?

1343


can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now

2240


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

2264


pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer

3239


pls mail some more tecnical qustions at msaranya2610@gmail.com

2183