Answer Posted / aneesh lal
If size is 300*200*150 mm
Volume of one block is 0.009 m3
So in 1 m3
1/0.009 = 111.111
Round off it.. u get 111 solid concrete block without wastage
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
How much percentage of brick bats allowed in CD-75 bricks
crank types
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
What are the alternate material for steel, Sand and aggregate
How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
What is packing Factor ?
afe or not
Which Types Of Bricks ?
Cement consumption of one cubic meter of aerocon blocks masonry?
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
wat would be the probable interview questions and GD topics for IOCL exam?