how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / er. tiwari karan
M25:: 1:1:2 Total parts is 4 Cement part is 1/4
Dry Volume of M25 is approx 1.57 times of total volume
Density of Cement is 1440
Cement Required for 1 cum =1/4X1.57X1440=565.2 approx cu. mtr.
for Bags (india cement bags) is of 50kg so 565.2 kg /50kg = 11.304 bags per cu. mtr.
So as with sand
dry volume if always 1.57 for required volume
and aggregate sole qty of aggregate if crushed to get 1 cu. mt we required 1.57 cu.mt
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
how many tonnes equals to one cubic feet?
Describe the role of independent Quantity surveyor?
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
What is meaning of tlc
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever
Why should appointment store person for project ? what is the benefits for company ?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
Which is the best book for building construction?
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
what is hydrostatic paradox?