how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / er. tiwari karan
M25:: 1:1:2 Total parts is 4 Cement part is 1/4
Dry Volume of M25 is approx 1.57 times of total volume
Density of Cement is 1440
Cement Required for 1 cum =1/4X1.57X1440=565.2 approx cu. mtr.
for Bags (india cement bags) is of 50kg so 565.2 kg /50kg = 11.304 bags per cu. mtr.
So as with sand
dry volume if always 1.57 for required volume
and aggregate sole qty of aggregate if crushed to get 1 cu. mt we required 1.57 cu.mt
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
Would you cause a 55-gallon drum of water to weigh more by climbing in?
Will water damage concrete?
what is SDLC ?and write a 'c'program for to swapping the three numbers?
what is moment-curvature relationship in semi rigid connections??
Explain how you can turn off the display for dimension in CAD?
What is the standard rate of installing ties for column(60cmx60cm) and beams(50x850)(weight)
which type of instrument included in plumbing work?name of instrument?
where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?
What is the snap size in civil and how can we create it?
Define What materials were used to build the Golden Gate Bridge?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
What is need for setting limits?
When was the first motorway built in england?
why are you joining in this (applied post) job and your aim for this job
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?