Answer Posted / thiyaneshwaran shanmugam
1) 1 Carpenter + 1 Helper - 5.5 - 6.5 Sqm/Day
2) 1 Steel fitter + 1 Helper - 150 - 200 Kgs/Day (Cut, Bend, Placing)
3) 1 Maon + 1 Helper - 10 Sqm/Day (Blockwork)
4) 1 Mason + 1 Helper - 12 Sqm/Day(wall plastering)
5) 1 Mason + 1 Helper - 10 sqm/Day(Ceiling Plastering)
6) 1 Mason + 1 Helper - 8 Sqm/Day(External Plastering)
7) 1 Tiler + 1 Helper
12 Sqm/Day (Vitrified Tile)
10 Sqm/Day ( Ceramic floor Tile)
8 Sqm/Day ( Ceramic wall Tile)
| Is This Answer Correct ? | 105 Yes | 3 No |
Post New Answer View All Answers
Why are steel plates inserted inside bearings in elastomeric bearings?
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
what is the dimensions of river sand truck trailer or trolly ?
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
Explain the latest method to detect a crack in a building?
how to calculate number of bitumen for road asphalt
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
pls mail some more tecnical qustions at msaranya2610@gmail.com
how to calculate the scour depth
what is stressing
to minimize budget cost of building , what can i do
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
Why the statue of liberty is made of copper?