Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

ACCOUNTING AND FINANCIAL ENGINEERING - EXAMPLE 34.27 : A biochemical engineering consultancy applies construction accounting in its finance. Its project began on 1 January 2010. Total revenue generated from the project was $9000. On 1 January 2011 as the budget, $2000 had been spent, with $6000 expected. However, the project cost increased latter, causing deviation from its initial budget on 1 January 2012, where $7000 had been spent, with $1400 expected. Let (estimated total cost) = (spent cost) + (expected cost to be spent), (percentage completion) = 100 (spent cost) / (estimated total costs), (total expected profits) = (total revenue) - (estimated total costs). Calculate : (a) total expected profits on 1 January 2011 and 1 January 2012; (b) estimated total cost as and not as the budget; (c) percentage completion of the project since the project began, in the first and second years.

Answer Posted / kangchuentat

ACCOUNTING AND FINANCIAL ENGINEERING - ANSWER 34.27 : On 1 January 2011 (as the budget), estimated total costs = $2000 + $6000 = $8000, total expected profits = $9000 - $8000 = $1000, percentage completion on first year = 100 ($2000 / $8000) = 25%. On 1 January 2012 (not as the budget), estimated total costs = $7000 + $1400 = $8400, total expected profits = $9000 - $8400 = $600, percentage completion on second year = 100 ($7000 / $8400) = 83.33%. Final answer : (a) Profits : $1000 (1 January 2011), $600 (1 January 2012). (b) Costs : $8000 (as the budget), $8400 (not as the budget). (c) Percentage completion : 25% (first year), 83.3% (second year). The answer is given by Kang Chuen Tat; PO Box 6263, Dandenong, Victoria VIC 3175, Australia; SMS +61405421706; chuentat@hotmail.com; http://kangchuentat.wordpress.com.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can any one send me the sample test papers of IOCL entry exam to be held on 6th july 2008. Also plz send the interview questions that cud probably be asked........i wud be highly obliged if u can send a few test paers and other stuff @ inderjeetd@gmail.com.........Inderpreet

2649


What is a "saltation velocity"?

1001


What is the best way to control an oversized, horizontally oriented shell and tube steam heater?

1080


marketing procedure of iocl

2322


Define octane number?

976


Can condensate control in a reboiler cause water hammer problems?

1091


How can you separate hydrogen peroxide into hydrogen and oxygen?

1053


How can viscosity affect the design of a mixer?

1059


what is the cast iron grade of composition of c-3.06% , Mn- 0.48% , Si-2.38% , S-0.088% , P-0.092% , Cr-0.12% , Ni- 0.012% , Mo-0.00%

2088


what r the question asked in interview of gate,is it related to course?

2258


Do you have any idea on recombinant protein expression?

976


What is cathodic protection, how it works in Turbine condensers ?

2900


What are some common precipitating agents used to remove metals from aqueous waste streams?

1095


how does the properties of an element changes by increasing protons and electrons?

2213


What is a good device to use for obtaining viscosity data for a non-newtonian fluid?

1180