How many no of bars in a bundle of steel and kgs/bundle. 8
mm, 10mm, 12mm, 16mm, 20mm with both MS and TMT separate.
Answer Posted / abdullah
before you calculate bars/bundles; you need to know the stander theoretical weight for one bundle is 2000 KG (2 Tons) and the common length is 12 M. this information is enough to tells there is a different number of bars per bundles for each size.
then, there is two way to calculate the number of bars per bundle:
first; bundle weight / ( PI x ( (bar size)^2 / 4 ) x steel factor x length )
for our information on top you will got; 2000/((PI()*D^2/4)*0.00785*12), where D for diameter of the bar (size you need)
second is; 2000 / ( ( D^2 / 162.163 ) x 12 ), where D for diameter of the bar
from this the stranded of no. of bar came to be:
12D=188, 14D=138, 16D=106, 18D=84, 20D=68, 25D=44, 32D=26, 36D= 21, 40D=17.
Is This Answer Correct ? | 12 Yes | 2 No |
Post New Answer View All Answers
Explain what are the skills required to become an architect?
Civil engineering related
What is the diff b/w ROAD TUNNEL & RAILWAY TUNNEL ??
All aptitude question of Bechtel
How much percentage of brick bats allowed in CD-75 bricks
how much cement is consumed by a stone masonry wall 17.7m long,0.55m wide and 1m high
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
What are the advantages of cad software’s?
How to find out kg per Sft ?
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
Whats the meanig of ,'K' VALUE in the case of soil.....
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
how to create our resume?
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?