How can i calculate the amount cement, steel , sand nd aggregate reguired for 1000 sq ft of r.c.c?
Answer Posted / utpal
first of you decide the depth of concreting work & use grade of concrete and fe fo steel grade and after that calculation of all this quentity
for example of 1 cum concereting work that means 1m x 1 m x 1m so that
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how gradation of aggregates effect on slump of fresh concrete?
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
how we calculate the grade of the Bituminous materials.?????
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
what is the formula for Mass of cement grout (Dg)=???
what is column foundation
how i get all type of short type question answer about civil engg
how to calculate MR 9(derivation)
Permissible wastage of cement as per IS code ? In which IS code I get it?
Explain moment of inertia?
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
Which is the direction for positive angle?