How can i calculate the amount cement, steel , sand nd aggregate reguired for 1000 sq ft of r.c.c?
Answer Posted / utpal
first of you decide the depth of concreting work & use grade of concrete and fe fo steel grade and after that calculation of all this quentity
for example of 1 cum concereting work that means 1m x 1 m x 1m so that
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What goals do you have in your career?
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
How to calculate canal slope curvature qty!
Permissible wastage of cement as per IS code ? In which IS code I get it?
What will you do if you encounter problems like accidents?
Need help in designing a degasser tower for 2m3/hr DM plant, also send me the formulae used
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
What is the use of offset command?
what is kribs is supporting?
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
I have to conduct load test on greting cover, pressure gauge is in kg cm2, how to caluculate load on this greting cover.
i have span of 6m x 4m how do i calculate the reinforcement of steel i needed and to at what distance and also the thickness of slab. looking forward thank you RAVI
what will happen if one could not properly follow the spacing of slab reinforcement bar?
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
What is Architect-Prepared Contract?