How do you calculate qty for form work like props shuttering
sheet and acro span for residential block ?
for Example: 10 sq mt what is the material and qty require to
do form work.
Answer Posted / thamaraikani
simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos
| Is This Answer Correct ? | 6 Yes | 3 No |
Post New Answer View All Answers
How to determine thee cut length for steel reinforcement bars in R.C.C design
plz drive the formula d2/162.162 for the calculation of weight of steel bars????
according to the painting co efficient, we should take the one side of doors (or) windows or both sides?
How to construct a water sump in a rocky soil?
what course did you consider thinking before you enrolled in college?
1.Fe500 and Fe550 having more yield strength than Fe415.But why are we prefering Fe415.? 2. d^2/162 formula for knowing the steel wt/m apply all these three? Thanks.
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
how do we design mix ratio?
how to calculate valuation for the old building?
Explain creep?
What is the best type of wood glue?
What are the applications of modulus of elasticity?