How to calculate the sand and aggregate in concrete
Answer Posted / manzar
For example M15=1:2:4
Sum of ratio=1+2+4=7
Consider volume=2 cu.m wet volume
Dray volume=wet volume+54%wet volume=2+54/100*2=3.08 cubic meter
Cement=3.08*1/7*1440=633.3kg
Sand=3.08*2/7*35.31=31.07 cft
Aggregate=3.08*4/7*35.31=62.14cft
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
Which is the direction for positive angle?
How to do base isolation using ETABS software?
What is the use of mirror command?
For a washout valve why are two gate valves required in normal practice?
though u r a civil engineer, y r u interested in tcs???
Which brick is best for construction ,either fly ash or AAC BLOCKS
What is thumb rule in quality and quantity estimation of a Residential building??
Explain what is Hybrid Foundation?
what are the types of dimensioning?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
what is called Bulk Density of aggregate?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
Explain the advantages and disadvantages of using plastic and timber fenders?
how to frame the sentence in voucher pad ? Description : 1.Food Expenses during site visit 2.Stamp Paper approval expenses 3.Travelling expenses 4. sweet distribution