what is the CT of protection and CT of metering ? what is
class 5P10 & 5P20 and class PS ?
Answer Posted / tahir vora- reliance jamnager-
5P10 means the maximum permissible limit of error (accuracy limit) is 5% at 10 times rated current (Accuracy Limit Factor). CT will give ratio error of only 5% even if fault current reaches 10 times the nominal value (In), after that CT will start to saturate.
Is This Answer Correct ? | 4 Yes | 1 No |
Post New Answer View All Answers
lamination figures
How do i carry out or know the vector group of a Dyn1 and Dyn5 transformer
State the frequency for rc phase shift oscillator?
In MEP Services what are parts of STP and what are there function?
What are the different losses In a de mac1une'! t.xplam
during installation time of transformer and alternator which points we have to observed?
What is the difference between diode and a transistor in terms of the direction of current flow?
what is automatic voltage regulator?we can control the vlotage by using fuzzy controller in matlab?why we go for fuzzy?
difrent between vcb acb sf6 and mccb breakers
how could we calculate the no of outgoings from a 800 watt distribution board
if there are six generators (3 gas CATT, one Jenbacher o1 MW each, and two nos Diesel 01 no 01 mw other 0.65mw EDGs ( say), 3 CAtt gas set have identical pole pitch,01mw EDG and Jenbacher gas Set have different pole pitch, how their power connection can be done to connect a common bus bar during installation. in short, how different pole pitched generators power connection can be done to connect a common busbar system through generators incomer ACBs.
electrical ques
We have 750KVA DG set, we want to introduce REF relay with 1250/1A,CL PS,Current transformers.The lead distance of 2.5mm copper flexible cable from CT to relay is around 5mtrs.We would like to know the knee point votage(VK) & IM calculion for CT's
can you plz send l&t aptitude questions if available its urgent plz plz plz
What is distance between electrical panel to land ?