If a load test has to run for 4 hours with 2,000 users, and
the average iteration completes in 10 minutes, how many
transactions will run per minute? can any give the calculation
please.

Answer Posted / sharmila rahman

Time taken for one iteration to complete = 10 min
No of iteration completed in one min(1 User) = 1/10 = 0.1
No of Iteration completed by 2000 users in one min = 0.1*2000 = 200

Is This Answer Correct ?    12 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the latest version and language used in load runner?

629


How do you identify which protocol to use for any application?

557


How to configure yahoo cookies in load runner?

2411


What is a ramp up and how it can be set?

632


Hi all, I am having an interview on LoadRunner (SAP Web Protocol). I am wondering if somebody can help me with some interview questions at a 2 yr Scriptor level. Thanks and all answers are much appreciated.

6280






How are concurrent users differing from simultaneous users?

592


What is gui vuser and on which platform it will run?

589


What are different types of vuser logs which can be used while scripting and execution? What is the difference between these logs? When you disable logging?

613


How can we edit the vuser script?

606


Why do you create parameter?

531


what is remote performance monitering?

1681


Suppose ur app server is .net server. In that connection pool is related to memory ?explain how?

1898


Which components have you used in loadrunner ?

564


How we tested remote servers if client is installed in another place

1711


What is protocol function?

607