Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.
Answer Posted / arbaz shaikh
16922sq ft=basement,
32022sq ft=super structure rehab
69087sq ft= for sale structure
Scope of work-rcc work,brick(siporex)block work,plaster.
Concrete(m-25 to m-50) -1.25cft.Sqft of bua,(for super structure.
4cft sqft of bua (for basement)
Consumption of steel(fe 550d) -5.5 kg sqft of bua for super structure.
12 kg sqft of bua for basement
What should quotation for this please guyz help me out .?
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is Brest Wall?
Scaffolding IS code NO.
1:4:8 pcc calculation 591 cu.ft
How much 1 cum of M15, M20 & M25 concrete weigh?
What is different between DI Pipe and CI pipe?
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
In which code the the maximum height of concrete casting has been explained
How do we test on design and style in a software?
For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)
Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in
Advantage of Aluminum form work in terms of activities can be skip and cost too
Stringer How many cm goes to landind
how much of the strength comes from post-production curing
How many days should curing of plastering, brick work and concrete
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.