actual volume brick ------- 19cm x 9cm x 9cm = 0.0015m3 (1m3/0.0015)=666.66 nos
thickness of mortar -------- 10mm
volume of brick + mortar------- 20cm x10cm x 10cm =0.002m3 (1m3/0.002)=500 nos
=(1m3 -500/666.6)
=0.25m3 of mortar
quantity of cement required
unit wt of cement 1440kg /m3
ratio 1:5
=1440/5
=288kg/m3 x 0.25m3
72kg/50kg per bag
=1.44bag of cement
sand
0.25m3
9cft

Is This Answer Correct ?    10 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

about higyway engineering

3543


what is the difference between replacement of cement by groundnut shell ash

2501


How you can turn off the display for dimension in CAD?

628


why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..

2069


Civil engineering material testing Standard results

1857






strength vs shape factor

2123


What happens to Load at yielding ?

901


what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght

959


Name the main components of a cad gui?

1028


Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.

1713


why demand factor less then 1 ?

1763


Civil engineering related

1503


What are your future hopes for this job?

1825


1:4:8 pcc calculation 591 cu.ft

1795


Difference between lime, distemper and plastic emulsion?

1227