how can we calculate cutting length of a column ring
(300 x 600)
Answer Posted / faiyaj ansari
600-80=520
300-80=220
520*2+220*2+2*10d-2*5d
=1560 mm
| Is This Answer Correct ? | 13 Yes | 8 No |
Post New Answer View All Answers
Cement consumption of one cubic meter of aerocon blocks masonry?
How do you change a dimension value in solidsworks?
I what know about life time of frp tank plz explain about it specifications & other details
In a concrete grade C35A, C & A stands for what and equalent cube strength?
What are the advantages and disadvantages of using plastic and timber fenders?
What are the strongest shapes in building?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
how to caluclate sienerge qty in construction in ap
How good are the Weinerberger Porotherm bricks that are being used in construction in Chennai, India. Its being used in non load bearing walls and has a compressive strength greater that 35 kg/cm^2 and a density of approx.694 - 783 kg/m3.
what is the types of door's wood?
insted of bentonite we can use any alternate material in piling ?
very simple or less time consuming formula for reinforcement calculation by moment
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
Formula of area of crane hook
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations