I've beams dimensions of 9"x 18"x 45' please calculate the weight. Thanks
Answer Posted / mudasir khan
.75*1.5*45=50.626
So 1Cft =70.72kg
50.625*70.72=3580.2kg
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?
what is escalation?how it is done?
What is the tensile strength of marble?
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm
in the construction of residential building what type of tank are used?where?why & what is its purpose?
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
can stub column take the load as main column
how to calculate load bearing column
how calucate cement sand ratio for plstering
What is c.g.i sheet which used for roof??
how to workable concrete cube test M-25 design mix
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).