how to calculate shuttering measurement of beam and slab
Answer Posted / senthil473
shuttering work of horizontal members are generally called as, centering. centering works are measured in m2. shuttering area = the area of slab (take clear spans for finding area) + total depth of the beam (no. 1 and 3 which are parallel to each other) * the clear span of the slab which is parallel to the no. 1 and 3 beams + width of the beams * total center to center length of the beams + (total depth of the beam + total depth of the slab) * total length of all the beams.
| Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
What are the basic use of runners and standards of pipelines?
What is fineness modulus ? and its sieve # ?
Ratio for 4500 psi concrete
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
what is the effect of duration of earth quake on framed structures ?
Wats the formula of eccentric footing and how was calculated from concrete qty
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
How is make concrete cube?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
rate analysis for cement pointing 1:4 , for 100 sq m
what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete
is there any influence of water(used for mixing of concrete) on a weight of harndend concrete.
can any one tell me in detail footing estimation .. i am new here in dubai so facing lots of problem...
why the profile of shell of natural draught cooling tower is hyperabolic.
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.