cement ;1440 kg/m^3
concrete ;2406.53 kg/m^3
brick :1600 kg/m^3
brick masonary: 1920 kg/m^3
sand (fine) :1600 kg/m^3
sand (medium) ;1900 kg/m^3
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon
how can we construct building without foundation providing only grade beam at ground level
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
What is structural frames or systems?
what is education Cess.
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
60-70 grade of Bitumen is VG-30 ?
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
How much cement,sand,bricks and water needed for 1square metre brick work?
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
all technical question
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
Difference between pre-tensioning and post-tensioning.
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order