Answer Posted / hassan bin mohsin

Formula for weight of steel bar D^2/162.2
For example
12×12/162.2= 0.88 kg per metre
Or there formula also be use
Unit weight of the steel × pi × d^2 / 4
For example
Unit weight of the steel is 7850
Pi value is 3.1416
Dia of the bar is 12mm
0.7850 × 3.1416 × (1.2)^2 /4 = 0.88
By using this to formula

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?

1671


in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?

1850


 What is difference between limit state and working stress method? How it is applies in building structure.

1774


I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?

1675


For The preparation of goverment examination Which book i will prefer and by which way i will do the preparation for exam.

1633






For removal of formwork of simply supported slab / beam from where to start the deshuttering? ( Max Bending moment of the simply supported beam is in the center hence is it required to start from the supports?)

1529


what is the use of water bar in water tank and is this an extra item in estimate?

2124


What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?

1815


what is right & short method of measurement of slab&beam

1586


How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance

2433


Define What is rigging?

634


Describe the various methods of concrete curing?

686


Form where IS456 is adopted in 1978?

1499


How we calculate the service time of buildings

1434


In tower foundation, on the time of 3 mtr pit RCC casting if water and mud is their surface of PCC then what will be do?

2003