Mujhe koi ye bta do ki 1.54 hi ku lete h material ki quantity niklne ke liye
Sab jgha dhund liya bt samj nhi aaya mujhe koi alag aalag krke smjao ki cement m aggr. Dust m itne % wet or dry % hoti h fir kaise kaise 1.54 aaya kha se aaya smjao koi pls m confuse hu my calling nd wts app no. Is +919034604938
Answer Posted / bharat sharma
wet volume = 1.54 cum
dry volume = 1 cum
thats way we take generally wet volume for calculated
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Exterior Joints,define
Define What is an ice dam sock?
Which is the latest version of solidsworks?
why building got air crack? if it get in one particular are what is means?
What is soil enforcement?
what is a well
Howmuch bend to be provide for 200/600 BEEM
explain the advantages of total stasion
What is alternate bid?
WHAT DLC DESIGN IN CONSTRUCTION
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
How to marking the building
std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh