How much overlaping required for welding the
reinforcement bars in Columns & beams
Answer Posted / arindam
10 times the dia of bar
Ex : 20 dia of bar, so 10 *20 : 200 mm lap while welding
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Floor tile measurement? Wall to wall or skirting to skirting
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
Suppose a new brick wall is being constructed,and the courses and not aligned horizontally,what negetives can it cause?
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
what is column foundation
What is bylayer?
What is geopolymer based concrete?
what is the water-cement ratio of mix design while 30mpa in 7 days?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
why +1 to be followed for calculating the no of bars in BBS. Please explain
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
what is the function of GSB all class ?
how much cost of single coat 20mm thick plastering per sqre meter
please send me bhel questions on rupesh.017@rediffmail.com
What in bending moment, if a moment is free end of cantilever beam?