1) One mason per day how many cu.m work will do as per list
given a) Brick work,hollow brick work and cc block work and
plastering how many m2 per day 2) one carpenter per day how
many m2 will do as well as scaffolding how many m3
Answer Posted / jarrar siddique
1. Brick work in cement mortar in foundation and plinth 1.25cum (45cuft)per mason/day, or 600 Bricks/day minimum.
2. 12mm (1/2) plastering with cement mortar 8.00sqm (80sqft)per mason/day.
3. Supplying, fitting, fixing and removing shuttering & staging 7sqm/carpentar/day.
Is This Answer Correct ? | 77 Yes | 8 No |
Post New Answer View All Answers
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
How to make tiles floor step by step procedure?
Differentiate orthographic and isometric projections?
List out the types of roofs?
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
Which is the most prominent tower of world?
Why should you show Client/Engineer activities clearly on the project plan?
where can i get the previous question papers for rrb section enginerr (civil)
How do we determine the specific gravity of a cement?
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
Would you cause a 55-gallon drum of water to weigh more by climbing in?
Use of coping on terrace wall and in 4" wall is compulsory or not ?
How much area will be covered in 1 litre of Velvet touch paint in normal wall condition
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
How to increase a bearing capacity of soil?