Answer Posted / er.darshan
but we will not consider 9" brick masonry is sq.ft.
the measurement or payment unit is cu ft
if size of brick is Actual = 19*9*9 cm or nominal size = 20*10*10 ( with mortar joints )
so,
1m3 brick work 500 brick are required
volume of bricks = 500 ( size of brick , actual ya nominal )
hear i consider = actual size of brick = 19*9*9 cm
= 500 x ( 0.19 x 0.09 x 0.09 )
= 0.77 m3
= volume of mortar = 1 - 0.77
= 0.23 m3 ... wet volume
= 0.33 m3 .... dry volume.
| Is This Answer Correct ? | 1 Yes | 3 No |
Post New Answer View All Answers
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
how to create our resume?
Why nautical mile is different from statute mile?
I want to join bhel because
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
Different sizes of Hollow blocks and its weight. Thanks.
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
20mm thick sand face plaster on walls consisting of 12 mm the backing coat of c.m.(1:3)and 8mm thick finished coat of c.m.(1:1)including scaffolding, watering, finishing etc complete please calculator with methyl et et r u
What is the strength of cement?
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
what is the weight of 6000 psi concrete in lb/cft?
What is Rankine Cycle?
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How many Sft of Level Plaster per Kg
percentage of metal,clay or soil & water in water bond macadam roads to know the quantities for each in total volume of 11500 cubic meters