How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area
Answer Posted / syed abdul kadhir
For example span will be 10' * 10'
Sheetsize 3'*2'
X axis 3*3=9'+1 feet plank throughout 10'=9+1=10'
Y axis 2*5=10'
Total number of sheet will be 15 and 1feet plank (10')
Prob will be provide in each 2ft
No of probs is 15.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what are the challenges of being a team leader and a supervisor?
IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI
What are the methods of measurement? Describe it shortly
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
what is meant by residual strain?
what would be the design load of R.C.C Cooling tower per cell.?
explain fie benefits of using standard terminology in the measurement process
What is the tensile strength of marble?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
why the openings of sieves are square io size?
the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C