How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area
Answer Posted / syed abdul kadhir
For example span will be 10' * 10'
Sheetsize 3'*2'
X axis 3*3=9'+1 feet plank throughout 10'=9+1=10'
Y axis 2*5=10'
Total number of sheet will be 15 and 1feet plank (10')
Prob will be provide in each 2ft
No of probs is 15.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
silt%= silt volume/ silt+sand volume is this right?
how can we construct building without foundation providing only grade beam at ground level
What are the advantages of cad?
What are the applications of the modulus of elasticity?
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
What are the composition of a landfill?
Can we use concrete of slump cone in cube casting in which we have already measured slump?
why development length = 50D . why not 100D
what is the weight of 6000 psi concrete in lb/cft?
Questions related to civil.engg in company
What is type failure of road surface? how to repair the failure of road surface?
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
How much quantity of rod binding work by a rod binder per day
What is the difference between Rock And Murrum. How to claim that excavated material is not a murrum but rock.