Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the shuttering materials i.e MS sheet,Props,Acrow Spans,2'x3' Runner,4'x3' Runner & beam plywood bottom, sides in thumb rules in slab area

Answer Posted / syed abdul kadhir

For example span will be 10' * 10'
Sheetsize 3'*2'
X axis 3*3=9'+1 feet plank throughout 10'=9+1=10'
Y axis 2*5=10'
Total number of sheet will be 15 and 1feet plank (10')
Prob will be provide in each 2ft
No of probs is 15.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the challenges of being a team leader and a supervisor?

3906


IS THERE ANY JOBS FOR THOSE WHO ARE IN FINAL YAER OF ENGINEERING(CIVIL) IN MUMBAI

2152


What are the methods of measurement? Describe it shortly

2284


How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)

2123


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2499


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

2167


what is meant by residual strain?

2468


what would be the design load of R.C.C Cooling tower per cell.?

2058


explain fie benefits of using standard terminology in the measurement process

1871


What is the tensile strength of marble?

1233


WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?

2415


Requirement of cement, and steel 1:2:4 ratio concrete in 1128 Sqft area(Cement No of bags, steel in Kgs)

2040


in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?

2047


why the openings of sieves are square io size?

1664


the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C

2113