How will we calculate the number of cement bags in 6 foot by 6
foot footing?

Answer Posted / pavan

6 Foot * 6 foot* 6 foot ,first convert in to mts
1 foot = 0.3048 mts
so 6 foot = 0.3048*6= 1.828 mts
so 1.828*1.828*1.828=6.11 Cum
according to mix design or nominal mix cement content will be provided per cum.
example if min cement content is 380 kg/cum for m30 grade
6.11 * 380 =2321.80
or 2321/50 = 46.36 bags

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??

1833


Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet

2349


what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?

2626


how to do cementicious paint for rcc walls of cw pump house

1539


what is mc arther pile?

1771






B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS

2533


what is the minimum cement content for M20 & M25 as per is code -456(2000).

2699


what is the 0 value in quantity surveying

1923


I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.

1557


Explain the design for rcc multi-storied building?

695


what is the use in canals of longitudinal drains and cross drains in lining areas?

1375


how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?

2137


Consumption of Binding wire for fixing of cover block in vertical surface

1033


what is the method used for marking of cantilevers in hirise buildings by using theodolite

2427


What is change order request?

670