how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / gurubardhan kumar
We have total 735cu.Ft
Ratio of m25= 1:1:2
Now calculate
Cement
1/4x1.54=.385
0.385x1440=554.4kg
554/50=11.08
731/35.314=20.7
20.7x11.08=230 bag
Sand
1/4x1.54=.385
0.385x20.7=7.969cuft
Aggregate
2/4x1.54=0.77
0.77x20.7=15.99cuft
#Ingredient=1.54
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
how i convert mm into standard wire guage (SWG)no.
What is the difference between undo & redo?
Detection of a beam & a girder areββββ
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
How to design staircase.plz tell me formula for the design the staircase.
what is tension footing?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
how to calculate quantity of bricks in circular manhole with examples.
how many material required for brickbat water proofing of toilets.
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
what is raft foundation
How to make a c++ program that converts any base to base 10?