how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / gurubardhan kumar
We have total 735cu.Ft
Ratio of m25= 1:1:2
Now calculate
Cement
1/4x1.54=.385
0.385x1440=554.4kg
554/50=11.08
731/35.314=20.7
20.7x11.08=230 bag
Sand
1/4x1.54=.385
0.385x20.7=7.969cuft
Aggregate
2/4x1.54=0.77
0.77x20.7=15.99cuft
#Ingredient=1.54
Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
how we calculate the grade of the Bituminous materials.?????
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
How many square meter can a worker/labor demolish a structure per day?
225 mm thick RCC slab, how many ton load slab can carry? for example if 33 ton truck loaded with soil, truck having 6 wheels. slab can take load or not? grade of concrete is M35 and slab design Fe500, slab desing one way slab.
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
How to calculate concrete in percentage wise ,for example cement 18% sand 40% aggregate 40% and Stell 2% ,I need and??
how many kg of 20mm, 10mm, dust available in one ton stone boulder
Technical Question of Civil Engineering
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
What is the difference between a wood shake and wood shingles?
procedure for preliminary selection of size of column of 5 storey building
what are the layers of the national and heir aprox thickness??
Basic civil interview questions
How do you calculate the power of centrifugal pump?