What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?
Answer Posted / maqsood
In simply supported beam lapping is not permissible.
In continuous beam
Top bars can be lap at L/3
Bottom bars can be lap before or after V.Support
Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
what is the use of beam end forces while using a staad ? wha they are show
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
Explain the mechanism of cavitations in pipes and drains?
How much cement,sand,bricks and water needed for 1square metre brick work?
I want to know about rolling margin of steel :- For eg. If 2nos. bundle of 8mm dia steel with17 rods each of length 12m comes to store. During testing of 1m rod of each bundle it was found that 1rod has weight .405kg/m while other has .385kg/m. Now what will happen in case of steel payment and measurement payment ? Regards,
what is the meaning of 40/20 src
Dear Sir I Mahesh C. Bhamre have already given a Exam for Superintendent Officer / Public relation Officer Exam Dharmday Aaukta held at Nashik on Date 29/08/2010. My seat no was 5040247. and my cell no is 9822677994. and my mail Id is - mahesh.bhamre@rediffmail.com So can you pl send me details of result of respective exams. Thanking you in Anticipation.
can any one explain bar bending schedule of bems and columns and slabs ??
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?
what is the difference between np2 and np3 concrete mix
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
What is Architect-Prepared Contract?
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
Write short note on construction programme for pile foundation.