What is the correct position of lapping splice of reinforcement steel bars in a beam at top & bottom of the beam?? what is the reason for this location?..what are the factors affecting lapping location in beam?
Answer Posted / saif rizvi
In simply supported beam lapping is not permissible.
In continuous beam
Top bar can be lap at the center or l/3
Bottom bar can be lap at l/3
This loction is as per bending moment
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
what is features of a typ-ical modern air-conditioning installation?
What is the difference between routing maintenance and major maintenance in school facilities?
how can we construct building without foundation providing only grade beam at ground level
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
What is the standard unit weight of Cast Iron pipe of 200MM Dia.(pipe specification is IS1538)
Critical Path Method is...
Under what circumstances should pot bearings be used instead of elastomeric bearings?
Types of column foundation and how to calculate its steel quantity.
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
Explain what is the release of lien?
Define relative co-ordinates?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Why is concrete cube test carried out?