Answer Posted / poras patel
Desired strength : S1
Achieved Strength : S2
Percentage Strength = S2/S1 x 100
if S1= 40 N/mm2
S2= 20
% strength = 20/40 X 100
= 50
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
what is the criteria for the finalisation of pavement thickness in road project?
What is the quantity of cement in mix m20 concrete?
How to estabilish reinforcement Steel rolling margin for a building projects ?
What is Heavy Concrete & Normal Concrete
what is pqc
reinforcement slab, beam and column formulas?
Slump Values for works?
What is semirigid connections?
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
Please design 12.5m long dubbly beam
Detection of a beam & a girder areββββ
Define What are the materials used in building a gravity dam?