Any body please let me know how to prepare Method Statement
for Bored Cast in situ piles.

Answer Posted / shubham rana

It is suggested that all utilities such as (cables, pipelines ,gaslines , sewerlines) falling within excavation area are diverted away in advance to avoid damage to such utilities during the excavation/ construction phase.

Initial hard strata of the ground is cut by a “Drilling Bucket” , which is a box like structure attached to Rig machine and has a sharp toothed like structure below it .

Then a temporary Mild Steel casing for about 4 to 6 m (approx) length from the ground level will be driven to protect loose soil from falling in the bore hole.

Then a Polymer Powder is added to form a slurry which provides a clear, solid-free, viscous borehole stabilizing fluid till the excavation is done for the piles. Polymer Slurry has a pH of 11 to 12, Specific Gravity of 1-1.04 and Viscosity 65 to 140.

After drilling borehole, reinforcement cage is lowered. While lowering the cage care has to be taken to install it in gap of 10 m and fillet weld of 6mm is to be provided to join upper end of previous cage with lower end of cage to be lowered.
After cage lowering , Tremie Pipe generally of diameter 200mm and 2-3 m length are lowered one by one and tied to each other . The gap between the bottom of the bore to the end of tremie pipe will be min 300mm.

Upper end of the tremie pipe is connecter to funnel shaped “Hopper” , to which concrete mix is poured .

As the Concreting Proceeds Concrete mix being denser replaces the Polymer slurry and slurry comes out of the borehole and is diverted away from the hole.

A very high Slump Concrete 150 – 200 mm is needed for piling ,regular compaction to be provided by Hydraulic Drilling Machine so as to ensure proper lowering of concrete .


After Few days of setting sonic tubes are filled with water and then in one tube ultrasonic wave emitter probe and in other receiver probes are inserted, knowing the distance between the two tubes , Relative energy, waveform and differential time are recorded and mapped. This is called “Cross Hole Sonic Logging”.

This gives qualitative idea of the structural soundness of the concrete throughout the pile and hence structural integrity of pile can be verified by this method.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the layers of the national and heir aprox thickness??

1593


what is tension & compression of steel bending.

1835


what is hydrostatic paradox?

1711


i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??

1640


Volume of 25kg putty bag & 40 kg putty bag volume??

1587






what is stressing

5807


PL.tell me about civil engineering questions with answer

2118


what is the meaning of degreasing of the euipment or line.

3306


What is an ortho mode?

716


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

1573


Permissible wastage of cement as per IS code ? In which IS code I get it?

1210


What are the advantages of cad?

641


please send latest placement papers of hpcl officers trainee test. i will be very thankful to you.

1816


WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?

2772


what is the minimum cement content for M20 & M25 as per is code -456(2000).

2704