Why CT's shall not be kept open?
Answer Posted / azhar ali
Basically, current transform has a few turns one or may be two at primary sides and many turns on Secondary side.If the ammeter is removed, the secondary winding becomes open-circuited and the transformer acts as a step-up transformer due to the very large increase in magnetizing flux in the secondary core. This results in a high voltage being induced in the secondary winding equal to the ratio of: Vp(Ns/Np) being developed across the secondary winding.
Turn ratio=vp (NS/Np)=> VP=480 NS=160 V &Ns=1 Then,
Tr=480*160/1 = 76800 volts
So it will be very dangerous if the secondary is opened.Therefore short the secondary of CT if the current meter is removed from the CT having primary current.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Explain the fundamental difference between emf (electro motive force) and pd (potential difference) ?
WHY RATING OF VCB NOT LESS THAN 630A
at meter room 50 hrc switch installed,but there are not get earthing proper,so what happen?and 11kv transformer out put going in to hrc main 400a three nog each? so earthing is require for all switch? (some customer made earthing at there home.)
Is it advantages of having star-delta vfd than normal star vfd , if yes why?
how load of a turbo generator can be increased
Write the programming software name for LG, SIEMENS,Messung,AB
main difference between ac and dc?
On a 3 winding transformer YNynd11, how do you apply REF protection to the Delta tertiary winding that is supplying auxiliaries to a substation?
Why we make earth connection with Transformer Body and What will be the minimum size of copper wire as per code with respect to KVA rating of Transformer?
oltc of a transformer, how it works? and what are the equipment consist of describe briefly?
What is the difference between relays and contactor construction wise?
power transmission pole used one support , that only for support or earthing
how will we calculate the copper wire load..
Difference between drift current and diffusion current?
i installed 100kva ups. what KVA genset they should provid in input side? plz any update formula or ans with reason.