how to calculate cement bag in RCC
Answer Posted / karthik
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What is the difference between absorption & adsorption and sorption?
What is Refuse Area In High Rise Building ?
What is the use of water table & Kreb stone for drain
what is meant by shear center?????
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
Which is the direction for positive angle?
is basic cost of the material includes tax?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
what is m30 in concrete tiles
How to calculate the quantity of cement mortar 2" for mosaic tile fixing 12"x12"?
What is factor not to be taken in consideration in mix design?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?
What is the difference between tor steel and tmt steel?
what is called Bulk Density of aggregate?