what are the volumes of soil stabilization mix of cement,lime
and sand in the ratio of 1:1:10 respectively in 1m3?
Answer Posted / gaurav srivastava
cement-0.083 m3
lime-0.083 m3
sand-0.83 m3
for cement= (1/(1+1+10))=0.083m3
similarly for lime
for sand= (10/(1+1+10))=0.83m3
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how much of quantity of material required for execution of one cubic meter of random rubble masonry in 1:3 cement mortar
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton
Which code is used for tor & tmt steel bar?
Define What is passive earth pressure ?
What is absolute pressure? How absolute pressure is calculated?
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
How much 1 cum of M15, M20 & M25 concrete weigh?
what is the use of water bar in water tank and is this an extra item in estimate?
what is the function of GSB all class ?
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
What is the largest concrete dam in the world?
why we are useing plastic under the lean concrete?and whts the advantage?
How to calculate the quantity of ingredients of M20 grade concrete?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.