How many kilo of binding wire required for one ton of reinforcemet steel binding?
Answer Posted / s k nishad
Per ton 70 kg binding wore used
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
Why are steel plates inserted inside bearings in elastomeric bearing?
what is the difference between natural draught cooling tower and induced draught cooling tower
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
Gave a cantilever beam with 3 legs.Told to draw the bending moment diagrams, axial force diagrams and shear force diagrams.From BMD he asked to show how the reinforcement will be provided on the tension side.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
What was asked in isro civil interview
How is the leaning tower of pisa supported?
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
explain five benefits of using standard terminology in the measurement process?