how many brick in 1 cubic meter with mortar ?
Answer Posted / aftab
cubic meter contains 500 bricks
The Standard size of the 1st class
brick is 190mm x 90mm x
90mm and motor joint should be
10mm thick
So brick with motor=200 x 100 x
100.
Volume of 1st class brick = 0.19 x
0.09 X 0.09 = 0.001539
cu.m
Volume of 1st class brick with
motor =0.2 x 0.1 x 0.1=0.002
cu.m
No. on bricks per 1cu.m= 1/
volume of1st class brick with
motor
=1/0.002
= 500 nos of bricks.
So 500 bricks needed(aprox).
| Is This Answer Correct ? | 11 Yes | 1 No |
Post New Answer View All Answers
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
Define What are the uses of Groynes?
how much shouid be the rate for ready mix concrete per cubic meter
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
for pretensioning which will yield first and same for post tensioning?
how we check the thickness and line of ceiling plaster.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
what are the five benefits of using standard terminology in the measurement process?
Explain different types of rcc pipes.
if i have to draw bending moment diagram of 4 way continous span then how to create it and how to find reaction?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
What Are The Steps Involved In The Concreting Process, Explain?
What is need for setting limits?
How can we convert weight batch to volume batch for m30 mix
Why should pumping be not used in case of concreting work?