Answer Posted / carl_ellis
Termination involves cutting and stripping the instrumentation wire, dressing the shield/screen with insulation on one end, installing crimp ferrules and connecting the wires to the screw or spring terminal terminal blocks.
Tradecraft includes maintaining the integrity of shield/drains at field instruments, junction boxes and marshalling panels.
Carl Ellis
Measure First
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is difference between radial vibration and axial vibration explain in detail .
what is the process for double acting cylinder pneumatic for 32' v/v
find the kp ki kd from the transper function G(S)=29.44s+04707/1.5349s2+s
Isometric drawings are generated during _________________ phase of a project
how works encoder in plc
how does we calibrate a square root flow transmitter ,give an example and explain it step by step like range calculation , calibration hook up series connection , zero check , and how to apply pressure , and if not geting proportional output then what should we do ?
please send the sample qustion paper for iocl written test ..
Instrument QA/Qc what is the project quality plan?conduit inspection RFI. which documents attache with package?
What is the difference between working pressure and calibration pressure of a control valve
what is intrinscily safe system and where we use?
What inherent design and operating principles are included in a modern control system to use predictive maintenance practices to increase overall system reliability?
what is stroke check for field instument transmetter's & AOV's
Isometric drawings are generated during _________________ phase of a project
what is different between 2,3&4 wire rtd and how much maximum distance using plc to field.
What is stripper & spilitter ? Diffrence in this.?