How to calculate the sand and aggregate in concrete
Answer Posted / muhammad azam
for example concrete ratio 1:2:4
volume or dry conrete=1.54
sum of ratio=1+2+4=7
cement=1/7 *1.54=0.219
sand=2/7 *1.54=0.439
aggregate=4/7*1.54=0.879
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
if size is 235cmsx15cmx100cms so how many cement bags and how many sand bags are used for concrete mix
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
detailed calculation of the amount of cement used?
why top layer of block work shoud be full size if any cut block adjustable than another layer?
how we calculate the vol.of wet concrete..?
Explain what is progress payment?
can i get civil engineering test papers.......?????
How to find CN by using arcgis 9.3?
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
Why are steel plates inserted inside bearings in elastomeric bearing?
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?