When you received a RA Bill of contractor at HO duly checked
and certified by Site In-charge, How to know at a glance it is
complete in order, do have any one checklist format in this
regard.
Answer Posted / vikas d v
every Ra bill have previous and present amount to be paid if its typical floor or if u know the quantity of items u can easily know
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Why should you consider yourself fit to be hired by jindal steel.
Rate analysis for construction of a solid block masonary of size 400x200x200 in C.M.1:5 in superstructure .Compressive strength 5.00 N/Sq.mm Confirming to IS: 12894:1990, with necessary scaffolding, raking of joints and pointing the same. I require rate per Cum.
What is command line?
What is min thickness,min grade of conc & age of PQC ?
Why joints are provided?
what is density of 20mm coarse aggregate.plz send answer my below adress e.mail
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
Hollow block masonry in cement mortar 1:4, 40×20×20cms in superstructure take 10sqm.I want calculation of brick sand
What out turn civil works
what is the method used for marking of cantilevers in hirise buildings by using theodolite
Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
What ingredients with% found in ppc cement??
how i can tak Quantity of mortar in block work
How to arrive dry volume of concrete (1.52 to 1.57) ?