Answer Posted / sandeep verma
Total length is 50 Mtr
Cutting length is 6 Mtr
Dia of bar is 32 mm
Standard lap length will be taken as 50D means 50 X Dia of bar. Then it will be 50 X 32 =1600 MM
50MTR/6MTR = 8Nos + 1 = 9 no of lap.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is meaning of tlc
What is meant by Crystal Concrete?
What you understand by building codes?
Who built the sears tower?
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
60-70 grade of Bitumen is VG-30 ?
Why concrete barriers have curved surface profiles?
how to shuttering is used in slab
What is the exception critarea of cube?
what is the clear cover for shearwall?
weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand
can stub column take the load as main column
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
i just want to know how much require sand and cement for 1 sq.mt including wastage. Please guide me as soon as possible.
Define What is a kip?